Can I build a backyard home in Pierce County (unincorporated)?
Since 2023, Washington law lets most city lots hold up to two more homes. Pierce County (unincorporated) writes its own rules on top. Here’s what the code says, in plain English — and a free report on what may fit on your lot.
What Pierce County (unincorporated) allows.
The headline standards. Open any card for the full wording and the code section.
ADUs per lotUrban growth area: 2 per lot of record. Outside the UGA: 1Full wording
Urban growth area: 2 per lot of record. Outside the UGA: 1.
Max size1,000 sq ft in the UGA; 1,250 outsideFull wording
1,000 sq ft inside the UGA; 1,250 sq ft outside, including basements and attics and excluding garages
Max heightNot above the main house (at least 24 ft must be allowed)Full wording
Not above the principal dwelling, except one additional story over a detached garage; a minimum of 24 ft must be allowed unless the principal dwelling is shorter
Front setbackNo closer than the principal dwellingFull wording
No closer than the principal dwelling
Side setback5 ft inside the UGAFull wording
5 ft inside the UGA
Rear setback5 ft (2 ft at an alley)Full wording
5 ft inside the UGA; 2 ft at an alley
Lot coverageNo coverage row in the current tables — confirm with the countyFull wording
No lot-coverage or impervious row in the current zoning tables — the SF/MSF zones are now SR, RR and MH (Ord. 2025-516s / 2026-523s) and Tables 18A.15.040-1/-2/-3 cover setbacks and height only (SR: front 25 ft arterial / 15 ft other, interior 5 ft, rear 10 ft; 35 ft). Impervious limits may sit in Title 18J / the stormwater manual — UNVERIFIED — confirm with city
ParkingNone near major transit; otherwise per PCC 18A.35.040Full wording
None within 1/2 mile of a major transit stop; otherwise per PCC 18A.35.040
Where a city figure reads stricter than the state floor (RCW 36.70A.681), the floor may control — the report flags it for your parcel.
Living there, selling it, plans, time and fees.
Each answer is the code’s own wording, with the section it comes from. “Not published yet” means the city hasn’t posted a figure — the report asks the city, not the internet.
Are backyard homes allowed?
Yes
Minimum lot size
Lot of record
Do you have to live there?
Not stated in PCC 18A.37.120; prohibited as a requirement by state law inside the UGA
Can it be sold on its own?
Permitted by state law
Pre-approved plans
None found
How long the city takes
No permit-timelines page. PPW's 'Permitting with Pierce County' deck (Dec. 2024) gives the SB 5290 tiers — Tier 1: 65-day approval, 15-day review cycles; Tier 2: 100 days / 30-day cycles; Tier 3: 170 days / 60-day cycles — without saying which tier a residential building permit falls in. Ask the Development Center (response within 24–48 hours by web form)
Impact fees
ADU impact fees are 50% of the principal unit's: traffic (fee schedule effective Feb. 1, 2026) ADU $3,001 in TSA A/B, $4,875 TSA C, $1,233 TSA D (single-family $5,902 / $9,650 / $2,367) plus a $100 administrative fee per unit; parks 'calculated at half that of the primary dwelling unit' (PCC 4A.20.030); school and park fees are bedroom-based since Ord. O2026-531 (July 2026) with ADUs at 50% of the bedroom-based fee
The code is half the answer. Your parcel is the other half.
Lines and easements
Where the lot lines really are, which setbacks apply on each side, and whether a utility or access easement takes the corner you had in mind.
Critical areas and slope
Steep slopes, wetlands and streams come with buffers that no citywide number shows. The report reads the county’s maps for your parcel.
Sewer, septic, water, trees
Whether sewer reaches the lot or it’s on septic, where the water service is, and which trees a city protects — the things that decide where a unit can actually go.
What Pierce County (unincorporated) allows, what could fit on your lot, and a planning cost range. If something won’t fit, the report says so — and shows what might.
Where this page comes from.
Read from the Pierce County (unincorporated) municipal code and the city’s own pages on October 9, 2026. The same table feeds the HousUp report, so the report and this page never disagree. Cities amend their codes; before you design anything, confirm the current wording with the county.
- pierce.county.codes/PCC/18A.37.120
- pierce.county.codes/PCC/18A.15.040
- pierce.county.codes/PCC/18A.15.030
- pierce.county.codes/PCC/18A.15.020
- www.piercecountywa.gov/903/Development-Center
- www.piercecountywa.gov/6023/PALS
- www.piercecountywa.gov/DocumentCenter/View/142343
- www.piercecountywa.gov/8972/Traffic-Impact-Fee-Schedule
- pierce.county.codes/PCC/4A.20.030
- www.piercecountywa.gov/CivicAlerts.aspx?AID=7203
- RCW 36.70A.681 — the state floor for accessory dwelling units